Hwange Power Station Begins Expansion

The Zimbabwe Power Company (ZPC) yesterday started drawing down on the $1 billion facility extended by the Chinese Government through China Export Import Bank meant to finance the Hwange Power Station 7 and 8 expansion to increase electricity generation capacity of the thermal power station.

President Mnangagwa said that the Hwange Power Station project will push the country towards electricity self-sufficiency.

“When we went to China, we were given a loan facility of around $1 billion for Hwange 7 and Hwange 8 whose draw-down will begin this week (to kick start construction works for the capacity expansion). In the process we have created jobs for over 1 000 people,” said President Mnangagwa.

The China Export-Import Bank facility was signed in 2015 and work is expected to start in the coming weeks.

The contractors, Sino Hydro, are the ones who were also contracted for Kariba South extension, and are already on the ground.

Hwange Power Station expansion will go a long way in ensuring power security. Hwange’s units 7 and 8 are expected to strengthen the country’s electricity base load and this will push the country towards self-sufficiency. Zimbabwe consumes an average of 1 400MW daily in summer and 1 600MW in winter.

The Hwange Power Station expansion programme follows the commissioning of two units at Kariba Power Station early this year as Government strives to narrow the power deficit. Kariba South extension plant units are contributing 300MW to the national grid.

The country still imports power from Eskom of South Africa and Mozambique’s Cahora Bassa Hydroelectric (HCB). Daily, Zimbabwe produces an average of 1 200MW, pushing the country to import 350MW.

This post first appeared in The Herald

 

About Author

Leave A Reply